# Huawei SmartLogger 3000

This guide is relevant for Huawei Sun2000 SmartLogger 1000 to 3000a

## Supported assets

| Model | Modbus TCP | Modbus RTU | Validated |
| --- | :---: | :---: | :---: |
| SmartLogger 3000 |  |  |  |

## 1\. Log in

- Access the **local web user interface** of the SmartLogger.
- Use an **Installer** account.

[![Image](<https://docs.octave.energy/ems/integrations/assets/huawei-smartlogger/c178d2ff-image.png>)](<https://docs.octave.energy/ems/integrations/assets/huawei-smartlogger/c178d2ff-image.png>)

## 2\. Enable Modbus TCP Server

- Go to **`Settings`** → **`Modbus TCP`** (left-side menu).
- Fill in the fields as shown below:

[![Image](<https://docs.octave.energy/ems/integrations/assets/huawei-smartlogger/811f0910-image.png>)](<https://docs.octave.energy/ems/integrations/assets/huawei-smartlogger/811f0910-image.png>)

## 3\. Activate Power Control Mode

- Go to **`Settings`**.
- Select **`Active Power Control`** from the left-side menu.
- Enter the values as shown below:

[![Image](<https://docs.octave.energy/ems/integrations/assets/huawei-smartlogger/a786797d-image.png>)](<https://docs.octave.energy/ems/integrations/assets/huawei-smartlogger/a786797d-image.png>)

## 4\. Final Steps

1. Log out of the interface.
2. Provide Octave with the **Serial Number** of the Smartlogger (e.g. `10218054125`) and its **IP Address**.
3. Share the **injection tariff formula** with Octave, so PV curtailment can be optimized for the customer’s tariff.